Decathlon

Decathlon

Overview
The Milestone team completed a full flooring refurbishment of a 3,500m² retail unit spread across two floors in Leeds City Centre. The project required the removal of existing finishes, structural screed repairs, moisture control, and the installation of a high‑performance, durable flooring system suitable for heavy retail traffic.

Key Works

  • Removed existing vinyl using specialist stripping machinery across both floors
  • Used Isocrete PHS to refurbish and re‑strengthen areas of failed cement/sand screed
  • Installed Hydraseal DPM throughout to provide moisture protection
  • Applied Flowscreed Industrial Top as the substrate, delivering a durable base designed to withstand pallet trucks and continuous store traffic
  • Installed Flowfast Quartz to provide a robust, visually appealing final floor finish

Outcome
The refurbished unit now benefits from a strong, resilient, and aesthetically consistent flooring system across both levels. The completed works ensure long‑term performance, durability, and a clean, professional finish ready for retail operations.